The installation of the boiler KV-G-116.3-150 was completed on time.
The hydraulic tests of the boiler were successfully carried out in the presence of the boiler inspection expert from the Kiev expert and technical center.
According to the results of hydraulic tests, permission was obtained to install outer casing and lining of the boiler.
Installation of pipelines for grid water supply at the facility continues.