Completion of the operational and environmental and thermotechnical tests for the KV-G-116.3-150 hot water boiler of the first start-up complex at the “Poznyaki” heating plant

Operational and environmental and thermotechnical tests of a hot water boiler have been successfully completed.

During the commissioning tests, the optimal gas-air ratios were selected, the combustion mode was adjusted, and control parameters were registered.

According to the results of operational and environmental and thermotechnical tests of the hot-water boiler, hazardous emission concentrations were achieved within the load range from 20 to 100 Gcal/h, that meet the requirements of Directive 2010/75/EU. As a result, it became possible to conclude that the hot-water boiler No.5 at the “Poznyaki” heating plant is ready for conducting comprehensive testing.

Latest news

Update on the project to build a new pressure collector in the village of Borodyanka

Working meeting on the project for the reconstruction of the pressure sewer collector in Borodyanka

Restoration of critical infrastructure in Dmytrivka village of Kyiv region