The first stage of reconstruction of the overhead power transmission line 110 KV “Kharkovskaya-Lugovaya – TPP-5″ with crossing the bridge on P. Grigorenka Avenue has been completed.
Two existing reinforced concrete poles were replaced with MSP poles, with execution of new foundations, replacement of overhead line hardware, wires and the ground wire.
The bridge capacity for large vehicles has been increased due to use of poles with a height of 40 m.