The work on the second stage of reconstruction of 110 kV overhead power transmission line “Kharkovskaya-Lugovaya-TPP-5” has been completed.
In the course of the second stage of the reconstruction, the existing 10 lattice 110 kV supports of the obsolete type designed for high voltage transmission were replaced with MSP (multisided steel pole) supports, with execution of new foundations. Also, the replacement of the existing overhead line hardware, wires and ground wires with an increase of wire cross-section have been made, given the prospect of increasing the electrical load for power lines in the future.