According to the project “Internal power supply of the production base at the 9-th May str. in Kiev” electrical and commissioning work are completed.
Delivery, installation and commissioning of KTPGS-1000/10/0.4 were performed during these works and 0.4 kV internal electrical networks were laid.
Preparation for external power supply works of the facility has begun.