Update on the project to build a new pressure collector in the village of Borodyanka

ZEM—EnergobudTM, the general contractor for constructing of a new pressure collector in the village of Borodyanka, has completed the first 500 meters of the collector using horizontal drilling.
The NEFCO corporation finances the work.

The network length in a two-pipe version is 1506.5 m. The pressure collector is located on Central Street in Borodyanka. The work is being carried out without blocking traffic.