Construction of 10/0.4 kV 6 MW underneath transformer substation in the shopping and leisure center “Komod”

Project status:
Completed
Deadline:
august 2006 - february 2007
Customer:
Limited Liability Company “T.M.M.” LTD

ZEM-ENERGOBUDᵀᴹ PERFORMED THE WORK IN THE CAPACITY OF A GENERAL CONTRACTOR.

LIST OF WORK PERFORMED:
  • Design work;
  • Supply and installation of 6 1000 kVA dry type transformers manufactured by Merlin Geren, and also integrated switchgears KRU-10 kV and KRU-0.4 kV;
  • Laying of 10 kV cable line for external power supply and 0.4 kV cable line for internal power supply;
  • Equipment commissioning;
  • Object commissioning.