ZEM-ENERGOBUDᵀᴹ PERFORMS WORK AS A MAIN CONTRACTOR.
LIST OF WORKS:
- Execution of the construction part of the indoor 110 kV substation;
- Execution of the full range of electrical installation works, including: installation of 2×63 MVA transformers of the type TRDN, installation of SF6 insulated 110 kV switchgear/control gear, installation of vacuum 10 kV cubicle switchboard, 0.4 kV balance-of-plant switchgears and relay panels, telemechanics systems, automatic system for commercial accounting of power consumption, etc.;
- Installation of a full set of external and internal substation networks (communications, electric power supply, lighting, grounding and lightning protection, water supply and drainage, ventilation and air conditioning, fire alarm and fire suppression, security alarm and access system, etc.);
- Arrangement of access roads, landscaping and installation of fences;
- Supply of equipment and materials;
- Performance of a full range of set-up and adjustment works for all systems and equipment;
- Object commissioning.