ZEM-ENERGOBUDᵀᴹ PERFORMED THE WORK IN THE CAPACITY OF A GENERAL CONTRACTOR.
LIST OF WORK PERFORMED:
- Implementation of the project stage P and the stage R (working draft);
- Installation of the 10/0.4 kV package transformer substation; laying of 10 kV and 0.4 kV cable lines for the needs of construction;
- Construction of a 10/0.4 kV transformer substation with equipment supply and laying of 10 kV and 0.4 kV cable lines;
- Full scope of start-up and adjustment work;
- Object commissioning.