Reconstruction of 35/6 kV substation at the concentration plant “TsOF Komendantskaya”

Project status:
Completed
Deadline:
february 2010
Customer:
SE "Regionalnuye Elektricheskiye Seti"

ZEM-ENERGOBUDᵀᴹ PERFORMED THE WORK IN THE CAPACITY OF A GENERAL CONTRACTOR.

LIST OF WORK PERFORMED:
  • Designing of a two-transformer 35/6 kV substation with a capacity of 2×6.3 MVA and re-equipment of the double-circuit PL-35 kV for the project stage P (design works) and the project stage P (working draft).