Construction of 110 kV overhead power transmission line “TPP-5 - Arkada”

Project status:
In Progress
Period of execution:
started in 2017
Client:
Limited Liability Company “Arkada-Budivnytstvo”

ZEM-Energobudᵀᴹ performs work as a main contractor.

List of work performed:
  • Construction of a 110 kV overhead power transmission line “TPP-5 - Arkada” with the transition over the river Dnieper, including:
  • Dismantling of existing foundations, supports and wires of the existing 2-circuit 110 kV overhead power transmission line “TPP-5 - Lugovaya – Kharkovskaya”;
  • Execution of cast reinforced concrete foundations and installation of 18 multisided steel pole supports;
  • Complete reconstruction of 2 transitional supports across the river Dnieper H = 101 m;
  • Installation of a new 4- circuit 110 kV overhead power transmission line “TPP-5 - Arkada”;
  • Installation of fiber-optic link on supports;
  • Supply of all equipment and materials;
  • Execution of start-up and adjustment work; object commissioning.