Upgrading of 35/6 kV substation “RRZ” at the plant “Vulkan”

Project status:
Completed
Deadline:
march –december 2008
Customer:
Plant “Vulkan” LLC

ZEM-ENERGOBUDᵀᴹ PERFORMED THE WORK IN THE CAPACITY OF A GENERAL CONTRACTOR UNDER THE CONDITIONS OF THE EXISTING 35 KV SUBSTATION.

LIST OF WORK PERFORMED:
  • Dismantling of 4 MKP-35 type 35 kV oil switches, outdated sets of 35 kV current and voltage transformers;
  • Installation of 35 kV SF6 circuit breakers Siemens with re-equipment of 35 kV busbars, installation of 35 kV current transformers TS-35 and 35 kV voltage transformers TN-35;
  • Delivery and installation of relay panels;
  • Execution of start-up and adjustment work.