The development Program of the Converter Shop of PJSC “ArselorMittal Kryviy Rih” has been completed

Project status:
Completed
Deadline:
December 2023

The program for the development of the converter shop was put into operation and preliminarily accepted – for the device of the smoke removal system in the converter shop of ArcelorMittal Kryvyi Rih PJSC. As part of the project, the installation of the smoke removal pipeline and the cooling pipeline of the shafts, as well as the installation of the metal structures of the supports for them, was done. ZEM-Energobud TM performed production, supply, chief installation and chief commissioning of the equipment.
All indicators of the object laid down in the project were actually achieved.
Construction and installation works were performed in the period according to the calendar schedule for the relevant contract.