Projects

Completed: 2012-2013 years
Supply of station and turbine pipelines of high, medium and low pressure for Units 8 and 9 of the Cherepetskaya SDPP (Russia)
Completed: 2013-2015 years
Supply of turbine pipelines for new construction of Units 1 and 2 of the Leningrad NPP-2 (Russia)
Completed: 2015-2016 years
Supply of turbine pipelines for the Belarusian NPP (Belarus)
Completed: 2011-2013
Supply of pipelines for the Yuzhnouralskaya SDPP-2 (Russia)
Completed: 2011
Supply of parts for hot reheat pipelines for the Permskaya SDPP (Russia)
Completed: april 2013
Supply of pipelines for the Berezovskaya SDPP (Russia)
Completed: december 2016
Supply of a 10 kV switchgear for power supply of a residential complex
Completed: february 2017
Supply of electrical equipment for a power supply system of a residential complex
Completed: july 2017
Supply of 6 kV electrical equipment for construction of the ІІ phase of the heat supply station “Poznyaki” Kyiv
Completed: march 2017
Supply of live steam pipelines for the first power unit of the Belarusian NPP
Completed: june 2017
Supply of utility pipelines for the Belarusian NPP
Completed: february 2016
Supply of elbow bends for the oil and gas industry of Ukraine
In progress
Construction of 110 kV overhead power transmission line “TPP-5 – Arkada”
Completed: november 2016 - november 2017
Construction of ІІ stage of “Poznyaki” heating plant with a total capacity of 100 Gcal/h (116.3 MW)
Completed: 2009 - 2011
Reconstruction of old buildings and construction of the Production Complex “ZEM”
In progress
Laying of KL-110 kV cable line “TPP-5 – Arkada”
In progress
Construction of 110/10 kV substation “Arkada”
Completed: 2010 - 2017
Construction of the residential complex “Sonyachna Brama”
Completed: 2013 - 2014
Reconstruction of the kindergarten on Lomonosova street
Completed: september - november 2014
Construction of the residential complex “Frantsuzskiy Bulvar”
Completed: 2012 - 2014
Reconstruction of the district boiler house “Moskovskaya-1”